UK WATER INDUSTRY RESEARCH

My UKWIR

Water research theme

Water

This programme area includes research into both the demand for water and the supply of water, with the concept of the supply/demand balance driving much of the work. Subject areas include headroom, demand management/water efficiency research. Water quality forms a large component of this research area, including epidemiology and microbiological studies, cryptosporidium, metals and algal toxins. Research also includes asset location, distribution operation and maintenance strategies (DOMS) and pipeline innovation, with leakage projects taking a high priority to help water companies reduce leakage to their economic levels.

Much of this research has been in collaboration with the regulators so that basic methods and frameworks can be agreed and applied.


Programme Lead(S)

Jeremy Heath

Leakage
SES Water

John Haley

Drinking Water Quality & Health
Yorkshire Water Limited

Paul Merchant

Water Resources
South West Water Limited

 

Sub-categories



 

Projects


 

A radical re-evaluation of the use of stored water reservoirs

Project Status Project Completed

Storage of water in reservoirs is important for managing supply and demand. Water quality generally improves with reservoir storage. However, where the catchment contains the correct nutrients, some reservoirs experience problems with the seasonal growth of various taxa of algae. Algae in water leaving the reservoirs causes problems for treatment works, increasing chemical and energy costs of water treatment, and zebra mussel larvae leaving the reservoir can settle as adults in tunnels adding costs for cleaning tunnels and managing outages. Once these organisms leave the reservoir they have to be removed from the water and disposed of at further cost. Certain dissolved organic compounds such as polar pesticides are persistent in the environment, and may not be removed to legislative standards by current water treatment works technologies. New technologies will be hard to fit into existing treatment trains, and may be very expensive to operate. For these a low cost treatment solution is required.

 

Adoption of novel quantification techniques for microbial and viral microorganisms for water quality assurance

Project Status Expressions of Interest

UKWIR supported the EU Aquavalens project, the aims of which were to challenge and develop new techniques for the detection, quantification and identification of a range of microorganisms. This project will complete in early 2018, but is already showing the potential of some techniques to improve our understanding of the microbiological safety of water and give better knowledge of the raw water challenge.

The revisions to the EU Drinking Water Directive currently being discussed are also may broaden the range of microorganisms regulated.



 

BQ - Achieving 100% compliance with drinking water standards at point of use by 2050? - Phase 2 - Intensifying Natural Processes

Project Status Project Commenced


 

BQ - Achieving 100% compliance with drinking water standards at point of use by 2050? - Phase 2 - Understanding DBP formation: Interpretation of laboratory experiments to operational conditions

Project Status Project Commenced


 

BQ How do we achieve 100% compliance with drinking water standards by 2050? Better understanding of the chemistry of the control of lead

Project Status Project Commenced

Project

This project will address key issues in order to meet the outcome “Ownership and responsibility for water quality is clear and all part their part in its protection”. The project will improve our understanding of the complex chemistry which underlies the control of lead solubility.  Recent developments in analytical instrumentation open up a number of avenues to enhance the industry's understanding of the surface chemistry which facilitates compliance or causes failure.



 

Can passive sampling devices provide more useful data than discrete samples

Project Status Project Completed

Much of the industry's water quality data comes from targetted analysis from a bottle filled at a moment in time - leaving gaps in knowledge of days or weeks which are generally filled by interpolation

 

Catchment Management for Water Quality & Quantity

Project Status Project Commenced

The drinking water and environmental regulators have stated that they see the main effort to improve water quality / quantity to be based at a catchment level. This will aid the minimisation of algae, pesticides and colour in the raw water sources which in turn will minimise issues water companies face from taste & odour contacts.

The previous UKWIR project, “Quantifying the benefits of Catchment Management” was undertaken over 5 years ago and the project “Catchment Management – how do we know its worked” was started in 2015/16 but put on hold indefinitely. Catchment management has gained traction since then with some companies making great progress. The time is right for a review of the evidence, for or against, catchment management.



 

Cryptosporidium - enhancing industry's capability to respond

Project Status Project Commenced

There is an increasing trend for water testing laboratories, and water supply companies, to send all microscope slides on which Cryptosporidium oocysts have been seen to the Cryptosporidium Reference Unit, Swansea, for genotyping (identification of species). An internal audit of results at the CRU has shown that there is a positive relationship between typeability and the number of oocysts seen on the slides. However, most slides received had just one oocyst, and these are only very rarely typeable to the required level by current methods. This is largely due to the small amount of Cryptosporidium DNA present.


The methodology employed currently for Cryptosporidium slide genotyping uses optimised, validated methods for removal of Cryptosporidium oocysts from slides and optimised DNA extraction and purification from low numbers of oocysts; these were developed and validated as part of WRF project 4099. The PCRs developed and validated at the CRU for the UK water industry have been shown to be sensitive and specific for the detection and differentiation of all Cryptosporidium species and specifically C. parvum and C. hominis. For slides containing greater numbers of oocysts, the current strategy for unravelling mixed populations of Cryptosporidium spp. on a slide – by means of multiple PCRs each using small volumes of DNA samples - is successful, with a high rate of typeability and more than one species frequently detected. However, more recently there has been a trend for more slides with small numbers of oocysts to be submitted, and where there is a low amount of target DNA in the sample (from <5 oocysts), the strategy is less successful and a single, large volume assay may be more appropriate. The challenge is to design an assay that provides the required level of typing, and to introduce as much target DNA as possible in to the PCR mix without compromising the chemistry of the assay.


Due to the high demand the increased submission of slides with small numbers of oocysts places on laboratory resources, generating little in return by way of genotyping results, and following consultation with stakeholders, the CRU intends to temporarily withdraw the slide genotyping service for slides with <5 oocysts seen where these are not part of an outbreak or public health investigation of a water quality incident. This will allow staff to undertake the research and development work described below to improve typeability and sensitivity, while retaining specificity, for the future. This approach has been discussed with DWI and the Industry and accepted as a proportionate approach, facilitating the delivery of an improved methodology and service for the future.



 

Customer taps and their influence on water quality

Project Status Project Completed

A number of water quality failures at customers taps are directly attributed to the design and /or quality of the tap and fittings that are attached to the tap.

 

Developing management strategies for increasingly frequent algal blooms in source waters

Project Status Project Commenced

The development of phytoplankton in water supply reservoirs across the UK can cause severe treatment problems at water treatment works, resulting in a loss of output, increased treatment cost and, in extreme cases, threatening the continuity/resilience of water supply. Events of this nature are, however, relatively infrequent and may not occur for many years. This makes it difficult to plan for them and/or to maintain continuity in the measures required to reduce their risk and react to problems when they occur. In addition, continuity in monitoring and maintenance of records to assess the risk of these events is difficult to maintain.

As a result, water companies may be unprepared for extreme phytoplankton blooms and therefore not deal with them in the most efficient and effective way. This situation is unsatisfactory because there is an ongoing risk to continuity of water supply to customers, the primary legal obligation of water companies. Furthermore, the risk of these extreme events is likely to increase as there is a growing  body of evidence that suggests that algal blooms are occurring at times of the year when they have never or rarely been seen before and they are lasting longer, a possible result of climate change. If our changing climate is a driver for what we are seeing we need to establish clarity about the mechanisms involved in driving the change, so that we might understand just how bad a problem it might become.

 The Water Industry needs to ensure that the knowledge base to understand the risk of severe phytoplankton events affecting water treatment is improved.  It also needs to develop better planning proocedures to reduce the risk of these events and to manage them better when they occur. 

 



 

DWQ Big question - how can we achieve 100% compliance with drinking water standards at point of use by 2050.

Project Status Project submitted as Complete

UKWIR has undertaken an ambitious programme to define longer term, strategic research needs in key areas via its Big Questions initiative.  Drinking water quality (DWQ) is the third such area to be developed.  

Drinking water quality is of key importance to public health and provision of safe drinking water has been recognised as one of the greatest technological advances of the last century.  The future challenges in DWQ include: raw water quality deterioration due to climate change and related factors, increasing expectations of quality from both the public and the regulators, energy efficiency in treatment, and delivering quality with aging infrastructure. This review will consider all options for improving DWQ from catchment to tap and identify the most appropriate interventions.

A research programme for DWQ must consider improvements to existing drinking water infrastructure to maintain water quality in the face of source water degradation and limited resources - particularly in the short term – but then identify the potential possible shifts in the current drinking water infrastructure paradigm that might include partially- or fully-decentralised treatment, delivery of different grades of water quality, new materials, and innovative treatment processes in the longer term.



 

Emerging pesticides; what next? Stage 2: Trials of emerging technologies

Project Status Project Completed


 

Evidence review of catchment strategies for managing metaldehyde

Project Status Project Completed


 

GAC Quality and Operational Management including Regeneration, alternative adsorbents, ozone and alternative oxidation technologies

Project Status Project Completed

GAC is one of the mainstay processes of water treatment as it has multifunctional capabilities to provide a barrier against water quality challenges. There are more and more utilities now adopting the use of GAC for the first time. Also companies who are currently utilising GAC are trying to rationalise their GAC performance and management whilst trying to minimise the associated cost. The project will look at how to manage the sometimes conflicting views of cost vs quality of virgin and regenerated carbon from internal water and regenerating company perspective to enable the optimisation of performance and final water quality.

We are required to achieve compliance with drinking water quality legislation. The use of GAC is now widespread, but the original decisions for how to operate it were made 20 years ago. There have been changes in the manufacturers of GAC and in how it is regenerated. Operators have sought to optimise the way it is used. Some problems have been reported with the growth of animals. Many of the original GAC experts have left the water industry. There is a need to keep up to date with developments in the design and operation of GAC systems to ensure they are still fit for purpose and to assess how well suited they are to future challenges. This should inform PR19.

Existing GAC assets are unable to achieve regulatory compliance for emerging pesticides. Previous UKWIR research (DW14) has shown that changing how they are used appears to be both impracticable and unaffordable. A number of possible candidate products such as synthetic polymer adsorbents, or a silica based product, may partially or totally replace GAC in future. Previous UKWIR projects have not adequately evaluated them due to their timescale for development and availability in the market.

Ozone technology installed in AMP1 & 2 may be coming to the end of its useful life. What should replace it? Ozonation offers a range of water quality improvements and a powerful disinfection stage. In particular it was used for compliance with the pesticide regulatory standard. Most UK companies installed processes that were over designed regarding their capacity requirements hindering optimisation and potentially producing DBPs.

 

Implications of a revised EC Drinking Water Directive

Project Status Project Completed


 

Improved slug pellet formulations to reduce risks to water

Project Status Project Commenced

Despite several years of activity 2014 still saw significant numbers of sample exceedences for metaldehyde. 2014 also saw the removal from sale of methiocarb based slug pellets, reducing to two the actives ingredients available for slug control. There is the potential for an increase in the number of exceedences in treated drinking water as a result.  Consequently, there is a need to identify routes to improve the rain-fastness of slug pelletts; to identify potential improvements to palatability to reduce the number of pelletts needed for effective control and to identify potential replacement active ingredients which offer lower risks to water supplies.



 

Independent advice service on health significance of microorganisms occurring in drinking water

Project Status Project Completed


 

Invasive and Non-Native Species (INNS)

Project Status Project Completed

A new EU invasive species regulation will become law on 1 January 2015. The Regulation will ban €œintentionally or negligently€ importing, keeping, breeding, transporting, selling, growing or releasing species of Union concern.
Member states must analyse the pathways of introduction of listed invasive species within 18 months of the list being adopted. They must draw up action plans to address these pathways within a further 18 months.

 

Nickel Compliance due to Fittings - A review of risk factors and identification of potential control measures

Project Status Project Completed

There is a continuing level of non-compliance with the standard for nickel at consumers taps. In most situations the water supplied is nickel free and the non-compliance is due to fittings within the customers premises

 

Pesticide Risk Mapping and Catchment Interventions - PHASE 2

Project Status Project Completed


 

Sink to River - River to Tap - A review of potential risks from nano-particles & microplastics

Project Status Project Commenced

There is significant interest in the prevalence of nano-particles and microplastics entering the environment.

There is a lack of understanding for the water industry with regards to the occurrence, fate and behaviour of these particles during transport and Waste Water Treatment; once dischrged to the river system there is limited understanding of how these particles behave; if river water is abstracted down-stream there is a lack of knowledge around the occurrenceand degree of removal of these particles through water treatment processes.



 

Sustainability of Phosphate Dosing for WQ

Project Status Expressions of Interest

Phosphate is currently used by Water Companies  to provide a barrier between lead supply pipes and the water provided to their customers. This benefit only lasts while dosing continues. As soon as dosing ceases the barrier is removed and lead comes into contact with the drinking water. However, phosphate is a finite non-renewable resource so there will be a point when the dosing of this is unsustainable.



 

Toxicity advisory service - Microsheets

Project Status Project submitted as Complete


 

Treatment for new and emerging Pesticides

Project Status Project Completed


 

Water Quality Compliance - Development of Indices for the Future

Project Status Project Completed

Current WQ Indices produced by DWI and now used by OFWAT do not represent consistently the level of risk to public health or degree of customer impact.
The statistics underlying the indices are flawed and need to be revisited to fit the current needs of the Industry, its customers, and its regulators.

 

Toxicity Advisory service - Chemical datasheets

Project Status Project Completed


 

Toxicity advisory service - Toxicity datasheets

Project Status Project submitted as Complete


 

Active Leakage Control efficiency in the SELL calculation

Project Status Project Commenced

Both Ofwat and the Environment Agency (EA) have said recently that they have some concerns with the current Sustainable Economic Level of Leakage (SELL) process for the setting of leakage targets.  The recent EA guidance on leakage for Water Resource Management Planning (WRMP19) says :

There is increased realisation that SELL may not be the most effective way to plan leakage levels.  WRMP19 will be the final time that a leakage figure is derived from SELL.  We expect water companies to evolve and move away from SELL for WRMP24 and to innovate to reduce leakage beyond the current levels”.

 The Ofwat consultation document on outcomes for PR19 (February 2017) expresses a different view :

“Companies should report their SELL in business plans, explain their assumptions on future improvements in leakage reduction efficiency in the SELL, and explain how its Performance Commitment for leakage is appropriate in relation to SELL”. 

 There is a strong feeling amongst companies that leakage targets should continue to be based on a sound economic analysis.  However, the cost of leakage management relationship for SELL modelling is derived from analysis of the company’s own historical leakage management performance data.  It is therefore a valid criticism of this process that if a company has been historically inefficient, then this inefficiency becomes built into the SELL.



 

Asbestos Cement water mains deterioration and failure prediction models

Project Status Expressions of Interest

In the UK, there is approximately 50,000km of Asbestos Cement (AC) water mains, 60% of which have been in service for over 50 years, the majority (approximately 66%) being small diameter, 100mm or less. With time, it has been noted that the failure rate of AC mains is increasing, demanding the need of replacement which can cost around £5 billion.

Several studies have identified that the principal failure mechanism of AC water mains is:
- exposure to conveyed water that has an aggressive nature, typically low alkalinity
- exposure to aggressive soils, typically low pH
- failure of the joints, typically due to microbial attack on the natural rubber joint rings

All of the above deterioration mechanisms are directly proportional to time, i.e., the longer the exposure, the greater the level of deterioration. Whilst there may be opportunities to extend the life of such pipes through lining and pressure management, these interventions are unlikely to be a success due to the small diameter and long-term exposure to the aggressive conditions that has already taken place.

If the level of AC main failures (pipe and joints) continue to increase, this will impact on the number of interruptions to supply and levels of leakage.

This project will be a collaborative project with the Water Services Association of Australia (WSAA).



 

Assessing the underworld

Project Status Project Completed


 

BQ6. How do we achieve zero uncontrolled discharges from sewers by 2050? – Research gap analysis and barriers to implementation

Project Status Expressions of Interest


 

BQ6. How do we achieve zero uncontrolled discharges from sewers by 2050? – Surface water drainage from new developments

Project Status Expressions of Interest


 

Deterioration rates of long life low probability of failure assets. (For example Concrete structures, tunnels and impounding dams)

Project Status Project Completed


 

Impact of Customer-side Leakage Approaches

Project Status Expressions of Interest

It is estimated that about 25% of the leakage within a water distribution network is located on a customer's property and occurs within the pipe that is not the responsibility of the Water Companies. However, this is still included in the leakage figures that water companies report to regulators.

The customers can be divided into household and non- household. For household customers, water companies offer a range of solutions from providing free advice to free repairs. There is limited understanding of how these different policies ultimately impact on reported leakage levels and overall cost to the business. For non household customers, water companies don't provide free repair services as a part of their standard customer leakage policy. However, with the opening of retail market, communication with non-household customers has become difficult, slowing down the leak repair and increasing the level of leakage.

Water Companies are also increasingly installing smart metering which identify leaks with very low flowrates. This has challenged the industry to find such small leaks, which are not cost effective to repair, and can be difficult to locate.



 

Mains Cleaning: Best Practice Review

Project Status Project Completed

The cleaning of water mains has traditionally been a method of removing any deposits that have built up over time and can cause water to become discoloured. The benefits of mains cleaning can be varied and dependant on a number of factors, such as mains condition, system hydraulics, water chemistry, upstream influences (eg. service reservoirs, pumping stations, trunk mains), aggressiveness of the cleaning intervention, the customer management approach, the sampling frequency post cleaning etc.

There are a number of traditional and innovative techniques available to clean water mains. This project would look to assess the benefits of each of the cleaning techniques taking into consideration each of these factors.

Of particular interest would be the cleaning of unlined iron mains since there is a belief that cleaning of such mains causes more problems than it solves. Generally, the industry, has chosen to extend the life of these mains by relining, using various types of internal linings resulting in a % of unlined cast iron mains that is likely to be around 30% - 40% nationally. The unit cost to replace or reline such pipes will mean it will take many years at current rehabilitation rates before the issue of unlined cast iron mains is addressed, consequently there is a keen interest in assessing the efficacy of cleaning.

Optimisation of mains cleaning may result in the potential to defer OPEX.  Increased technical knowledge across the Water Industry will allow Water Companies to adjust strategies, etc, based on informed decisions.  This will also have an impact on discolouration as well as taste and odour. 



 

Managing water chemistry to control pipe corrosion rates

Project Status Project Completed

The pressure for water companies to meet the iron standard and reduce discoloration contacts has driven a number of very costly initiatives such as mains pipe replacement and flushing that appear, in some cases, to have yielded only temporary benefits.

 

Mapping The Underworld Multi sensor location tool phase 2

Project Status Project Completed


 

NUAG Phase 2

Project Status Project Completed


 

NUAG trial project

Project Status Project Completed


 

Review of the UKWIR National Failures Database

Project Status Expressions of Interest

UKWIR developed the National Mains Failure Database for water distribution mains and sewers more than a decade ago. This has helped the industry to achieve better understanding of failure behaviour, act as a source of company specific data and help in more research and development of national models.

However, with time the input of information into the database by Water Companies has dropped, as has its usage. Data entry is considered time-consuming and reporting is a challenge. Thus, there is a fundamental need to go back to basics and carry out a full review of the options for streamlining and upgrading the extremely valuable platform



 

Risk based approach to flooding

Project Status Project Completed


 

Service Reservoir Asset Management Toolkit

Project Status Project Completed

Service reservoirs and water towers constitute a major asset base in the water industry. Managing these assets effectively ensures operational efficiency and water quality confidence. To manage these assets now and in the future, it is vital that water companies understand best operational practises as well as potential future strategies to allow better risk management and minimise whole life cost.

There are few industry wide asset management and decision support tools available which encompass the asset lifecycle as a whole, from planning and construction, through operation and maintenance to renewal/replacement and decommissioning. This research will identify and share best practise for the asset lifecycle of service reservoirs and water towers and their component parts.

Critical to the project will be the use of the “Framework for Expenditure Decision Making”[1] (FEDM) approach developed by UKWIR in 2014/15.

 

[1]14/RG/05/40: Common Framework 2014: Framework for Expenditure Decision Making: Part 1 Scope Definition






 

The impact of reductions in leakage levels on reported and detected burst frequencies

Project Status Project Commenced

The Water Industry has very little knowledge of the impact of reducing leakage levels on the numbers of repairs that need to be carried out each year, nor on the relative proportions of visible and invisible leaks.

Introduction of performance commitments and changes in SIM, with associated rewards and penalties, has increased focus on the customer service aspects of burst and leak repairs, whether it is unwanted contacts, interruptions to supply or associated discolouration contacts. Customer Service impact mitigation costs will add to the operational costs for repair and consequential damage.

Historic leakage strategy has focused on Sustainable Economic Level of Leakage (SELL). Leakage strategy now must consider the customer acceptability aspects of leakage. Most customer views are based on the impacts of visible or reported leaks and the impact of repairs on customer service.

Single company data is insufficient to discern any impact due to leakage level as it is masked by weather and relatively static targets. Pooled company data, combined with planned AMP6 reductions should provide a data set to understand any increases in repair frequency, changes in proportions of visible leaks and the time period for change.



 

VISTA

Project Status Project Completed


 

BQ Achieving zero leakage by 2050: Project 1 - Use of smart meters and smart networks for leakage management

Project Status Project Commenced

Modern technology has made it possible to collect much greater quantities of data, and at higher resolution. Leakage analysis methods and leak detection technology have both made many advances in recent years, but data collection and manipulation processes have hardly changed. The basic principle of measuring minimum night flow into a DMA, and then subtracting estimates of household and non-household night use to give leakage, remains unchanged in the past 30 years.

However the recent growth in smart networks, and particularly the use of smart meters for revenue purposes, could offer many new opportunities for better leakage management. It is essential that these opportunities and benefits are identified now, so that water companies can take them into account when making their choices of which smart technologies to invest in.



 

A survey of practices for the detection & location of leaks

Project Status Project Completed


 

Achieving zero leakage by 2050: Project 2 - Incidence and causes of repeat bursts at old repairs

Project Status Project Commenced

Distribution Maintenance staff at water companies know well that many leaks and bursts, once excavated, prove to be at the location of a previous repair, and occur as a result of a failure of the old repair. However it is not known how much data is collected on this, and there is no quantitative evidence of the magnitude or significance of this problem at national level. Nor has there been any study of the reasons for the failures, i.e. whether they are due to deterioration of the clamp or other repair materials over time, or whether they are caused by faulty workmanship at the time of the initial repair.

Many companies do record the types of failure within their records of mains and service bursts. However these descriptions are often very brief (e.g. “pin-hole”), and the fact that the failure was at a previous repair may not be recorded. This project will initially assess the availability of suitable data, in collaboration with participating water companies. The UKWIR National Mains Failure Database may also be a valuable source of data.



 

Assessing the impact of a distribution burst driven mains renewal programme on leakage control effort

Project Status Project Completed

Previous research into the impact of mains renewal on leakage focussed on the actual lowering of leakage levels through extensive renewal. For mains renewal schemes targeting pipes in the poorest condition and typically covering say 5%-20% of a Districk Metered Area (DMA) leakage levels will not reduce, but does overall natural rate of rise  (NRR) improve and can we get efficiencies in active leakage control (ALC) activity from a more robust DMA infrastructure? Is it then possible to quantify the improvements in NRR and then estimate cost reductions to keep leakage level?



 

Best practice for Derivation of Leakage Cost Curves in ELL Modelling

Project Status Project Completed


 

BQ Achieving Zero Leakage by 2050: Phase 2 - Combining transient and steady state methods for acoustic leak detection

Project Status Project Commenced


 

BQ Achieving Zero Leakage by 2050: Phase 2 - Hydrant dynamics for acoustic leakage detection PhD

Project Status Project Commenced


 

Factors Affecting Background Leakage - Revisit

Project Status Project Completed


 

Fast logging for improved estimation of household night use

Project Status Project submitted as Complete

A number of companies are starting to utilise ''fast logging'' as a technique to separate continuous and intermittent flow using DMA meters, to support the separation of leakage and night use components. The longer term roll out of smart metering in the energy sector, and potential associated introduction of various tariffs could lead to changes in customer behaviour, with the potential for increased water as well as energy use during the night. This could lead to an apparent increase in leakage if the estimation of night use is not improved. This could also have consequences for the effective targeting leakage using DMA flow data. Improvements in efficiency are also a key driver for the industry, and improvements in targeting leakage management resources could be a benefit from improvements in key components such as night use. Improved estimation of night use could further improve the data behind a key component in the estimation of leakage for regulatory reporting.

 

Leak Detection on Plastic Pipes

Project Status Project Completed


 

Leakage from PE Pipework systems

Project Status Project Completed


 

The assessment of key parameters in leakage analysis

Project Status Project submitted as Complete

Three of the key parameters in the analysis of leakage data are:
- Average zonal pressure (AZP)
- Average zonal night pressure (AZNP)
- Hour-day factor (HDF)

In 2012, Strategic Management Consultants (SMC) published a report on €œA Review of SELL and its Integration with WRMP€, commissioned jointly by Ofwat, DEFRA and the Environment Agency. Among the recommendations of this report was the following:
There is a need to review the methodologies for assessing average zonal pressure (AZP), average zone night pressure (AZNP) and hour to day factors (HDF) as part of the WRMP process. An industry standard methodology is needed, which should take account of the need to change hour to day factors with different forms of pressure management.€

In other words, hour to day factors should reflect current pressure regimes.

A specific problem has been identified with the current method of calculating HDF. In some cases, when HDF has been recalculated following implementation of a pressure reduction scheme, the calculated leakage has risen rather than fallen.

 

Updating 'Managing Leakage'

Project Status Project Completed


 

WM08 Long term leakage goals

Project Status Project Completed


 

COP and guidance on water use restrictions up-date

Project Status Project Completed


 

Drought Vulnerability Framework

Project Status Project Completed


 

Establishing a robust case for effluent re-use Phase 2

Project Status Project Completed


 

Future estimation of unmeasured household consumption

Project Status Project submitted as Complete

A robust estimate of unmeasured household consumption is an essential component of Water Resource Management Plans, Business Plans and annual reporting. Estimates are currently obtained using consumption monitors containing a sample of the unmeasured property base. As the level of metering of household customers increases, so the pool of unmeasured customers reduces. Particularly under optant metering programmes, those customers remaining unmeasured are likely to do so for a reason, for example high or unusual consumption or being distrustful of meters or water companies.

 

Integration of behavioural change into demand forecasting and water efficiency practices

Project Status Project Completed

improve the understanding of customer behaviour and its significance in demand forecasting. Project WR01A €˜Understanding customer behaviour for water demand forecasting€™, which is due to be published in Summer 2014, was the first step towards this objective. The project has been well received by the community, but further work is required to allow customer behaviour to be integrated into forecasts. WR01A showed that an understanding of customer behaviour is also useful in improving the effective targeting of water efficiency measures. Such an understanding offers potential for more efficient water efficiency campaigns resulting in more predictable outcomes.
CU02 also highlighted the need to standardise the questionnaires that water companies use to collect information on their customers€™ and how they use water. This information is vitally important in the preparation of demand forecasts, allowing an understanding of current consumption and how this is likely to change in the future.


 

Reservoir control and maintenance

Project Status Project Completed


 

Revision to the UKWIR code of practice and guidance on water use restrictions

Project Status Project Completed


 

Understanding the potential impacts of shale gas fracking for the UK WI

Project Status Project Completed


 

WRMP - Risk based planning

Project Status Project Completed


 

WRMP 2019 methods - decision making process

Project Status Project Completed


 

WRMP 2019 METHODS PHASE 2: POPULATION, PROPERTY & OCCUPANCY FORECASTING

Project Status Project Completed


Click the categories on the left hand side of the page to view the sub-categories and related projects